- CryoSat-2 Storage phase has formally terminated on 24/03
- Unit with patched software to be replaced on launcher has been cleared by local customs on 25/03
- and was integrated on the Launcher on 26/03
- Electrical testing of this re-integrated launcher unit is planned on 29/03
- Radiation (communications) tests with the Space Head Module planned on 29/03
- On Spacecraft, Off to Launch mode successfully retested 26/03
- Spacecraft side A check was successfully retested 26/03 (check of side B to be completed on 29/03)
- Spacecraft battery charging started on 26/03 (to be completed by 29/03)
- Transport of the Spacecraft to the Silo on the Crocodile is planned on 1/4
- Transport of the EGSE/NDIU to the Bunker is planned on 1/4
- Battery Voltage + Electrical checks once Spacecraft mated on Launcher at TBD date
- A last venting of the Low Pressure Branches A and B (still under discussion)
- Dress rehearsal is planned on 6/4
- Last checks to be performed on 7/4
- Launch on 8/4 @19:57 Baikonur time from Launch pad 109 (15:57 CEST)
vendredi 26 mars 2010
Campaign status and planning
Few days after the campaign has resumed, the status to date is as follows: